Description

The Interactive Learning Pavilion will be a state-of-the-art educational facility that will enable UCSB to meet its current and projected enrollment growth, providing the necessary facilities to support teaching and learning on campus. The new building is sited in the heart of the UCSB Campus at the southern end of Library Mall and is designed as an extension of the campus experience. The Interactive Learning Pavilion is comprised of five tiered lecture halls, three active learning classrooms, and 20 discussion classrooms; in total, the new building will provide approximately 2,000 new classroom seats for the campus community. The form and materials of the building are inspired by the surrounding context, elevating the experience of campus with outdoor circulation and collaborations spaces across all levels featuring views to the campus and beyond. The project is targeting a minimum of LEED Gold certification and is designed as an all- electric facility without the need to use natural gas.

Activity

June 2021

Work in progress:

  • Setting up the crane for structural steel erection.
  • Excavation for the Stormtech water retention system in Lot 3.
  • Excavation for the Service Yard foundation.
  • Construction of the building mock-ups.

Completed Activity:

  • Site construction fencing, site demolition & clearing, construction trailers.
  • Underground utilities: sewer bypass, communications conduits, chilled water piping, recycled water main extension, fire hydrant relocation.
  • Mass excavation and mud slabs poured.
  • Mat slabs poured (appx. 4500 cubic yards).
  • Waterproofing and backfill of mat slabs is complete.

Completed Activity, previous related site preparation projects:

  • Relocation of Modular Building 383.
  • Construction of East and West Bike Paths.
  • Demolition of Building 408.
  • Removal of contaminated soil at Bldg. 408.
  • Signage and traffic striping on UCEN Road.

May 2021

Work in progress:

  • Formwork, reinforcing steel, baseplates and conduit placement for two concrete mat slab foundations (concrete pours scheduled for 5/8/21 and 5/15/21)
  • Waterproofing and subdrain installation for mat slabs
  • Prep for mat slab backfill
  • Structural steel in fabrication in remote shops
  • Preparation for construction crane installation

Completed Activity:

  • Construction trailers and fencing installed
  • Site demolition and clearing
  • Underground utilities: sewer bypass, communications conduits, chilled water piping, recycled water main extension, fire hydrant relocation
  • Mass excavation for foundation system
  • Three mud slabs poured
  • First concrete mat slab foundation poured

Completed Activity, previous related site preparation projects:

  • Relocation of Modular Building 383.
  • Construction of East and West Bike Paths.
  • Demolition of Building 408.
  • Removal of contaminated soil at Bldg. 408.
  • Signage and traffic striping on UCEN Road.

January 2021

Work in progress:

  • Install new manholes and underground piping for sewer bypass.
  • Install new underground chilled water piping.
  • Install new underground communications conduits.
  • Mass excavation for building foundations.

Completed Activity:

  • Site construction fencing.
  • Site demolition and clearing.
  • Investigation/safe-off of existing site underground utilities.
  • Preparation for construction trailer installation.

Completed Activity, previous related site preparation projects:

  • Relocation of Modular Building 383.
  • Construction of East and West Bike Paths.
  • Demolition of Building 408.
  • Removal of contaminated soil at Bldg. 408.
  • Signage and traffic striping on UCEN Road.